Initial Call

Example Sequence of Events
1.

Mid East Operator drills into fracture system in reservoir on horizontal well

2.

Experiences total loss of returns and subsequent kick

3. 

While attempting to regain control, a crater forms 100 m from rig

4.

Rig location is abandoned at daylight

5.

Operator initiates emergency procedures

6.   John Wright contacted 8 hours later

isba_1.jpg (10021 bytes)

  Operator's Actions   John Wright Co. Actions

7

Called JWCO to confirm availability

Availability to mobilize immediately confirmed.

8

Request manpower and pricing requirements

Requested information about incident for assessment

9

Assigned engineer to gather requested data

Consult with firefighters and Well Flow Dynamics

10

Get necessary approval for mobilization

Fax suggested initial team and pricing for approval

11

Fax formal request to mobilize to location

Mobilize 6 hours after initial call with team of 5 (1 engineer & 3 firefighters) from Houston and 1 engineer from Norway

12

Prepare visas and in-country transport

Arrive at location 36 hours after blowout