Syria 1995
|
Problem: During the
final angle building phase of this horizontal well, drilling fluids returns were lost.
After several unsuccessful attempts of pumping and spotting diesel and LCM pills to halt
the fluid losses, well control was lost. The well pressure exceeded the rupture limits of
the last casing string and a broach to surface occurred from the shoe of the surface
string. The BOP stack remained intact with the drillstring suspended 276m off bottom of a
1563m openhole section. The well was flowing oil and gas at extremely high rates. |
Remedial Strategy:
After two unsuccessful attempts to kill the well from surface through the drillpipe, a
relief well intervention project was planned. The well was flowing up the annulus at a
very high rate and hydraulic simulations showed that kill rates in excess of 75bpm with
15ppg kill fluids were required. Further investigation concluded that two relief wells,
intersecting the blowout well above the bit, would allow the necessary high kill rates and
an effective use of reactive plugging agents/mixtures. Although two direct intersecting
relief wells were required from the hydraulic calculations, the blowout severity, the kill
program complexity and the intervention time mandated that a third relief well could
provide reservoir flooding capabilities and backup options. |
Special Services:
Wright Boots & Coots was contracted to supervise the special services for this very
large blowout intervention project. This included technical planning services and on-site
supervision of well blowout control and engineering, hydraulic kill simulations,
directional drilling, well surveying, casing detection, kill fluids plant design and
operation, pumping plant design and operation, cementing, kill program design and
engineering and reactive fluids design and implementation. Vector Magnetics provided
electromagnetic ranging services and Ely & Associates provided pumping and reactive
plugging material expertise. Boots & Coots provided well blowout control services for
surface operations and kill fluid engineering was supplied by OGS. Well kill simulations
and engineering services were provided by Well Flow Dynamics. All special services groups
worked together with Wright Boots & Coots to create a single team. |
Challenges: The project
was complicated by the following:
- A multiple relief well intersection into a
blowing wellbore had never been performed in the industry.
- Intersection must be prior to the build up
section having an 8 to 12°/30m BUR. The presence of oil in the target annulus and three
converging wells required special planning and electromagnetic ranging detection
techniques.
- High flow rates required a kill program
having two intersections, spaced at 40m TVD apart, for efficient reactive plug pumping and
ranging.
- Local supply yards and services were very
limited and could not provide the required quantities and types of kill fluid materials
and kill plant equipment.
- All operations were integral to the ability
to place the two relief wells within the specified TVD interval and at the same
approximate time.
|
Results:
- Team concept for special services was
successfully and efficiently utilized.
- Electromagnetic ranging was effective in
locating the blowout wellbore.
- Two wellbores intersected the blowout at the
specified TVD interval and within three days of each other.
- A rate gyro was instrumental in minimizing
borehole position uncertainties.
- A 120 bpm total kill rate for 12 minutes
dynamically killed the blowout.
- Cement plugging with 2440bbls commenced
after achieving a static kill.
|